First, the operating procedures
1, driving method
1) The inspection must be carried out according to the inspection contents before operation.
2) When you hear the driving signal, you should be ready to drive.
3) Drive the dust exhaust fan.
4) First press the oil pump button, after starting the oil pump, when the oil pressure normally reaches the requirement (0.05-0.2MP) and the oil return is normal, turn on the cooling water, the water pressure should be lower than the oil pressure 0.05 MP.
5) Open the water seal tube and check the circulation condition. The water should be free of oil.
6) After the equipment is started for 3-5 minutes, it is considered that the operation is normal, and a small amount of ore can be started, and the load is gradually reached.
2, parking method
1) Before the parking, the ore must be stopped. After the ore in the crusher is finished, press the stop button to stop.
2) Close the water seal pipe and the water cooling pipe.
3) Stop the oil pump and dust removal equipment .
4) During operation, it is necessary to pay attention to whether the voltage, current, oil pressure and water pressure are normal, and should be accurately recorded on time.
5) Whether the operation sound of each part of the equipment is normal, the bevel gear rotation should not produce strong noise and periodic noise.
6) Observe whether there is a mixture of oil and water.
7) It is found that the motor smokes, ignites, and the oil return temperature exceeds 60. The machine parts are broken, the broken pieces are stuck, the spring is broken, and the vehicle should be stopped urgently.
Second, maintenance procedures
1. The operator should be familiar with the structure, performance, and the names, specifications, and functions of the components, and make reasonable use and full use.
2. The maintenance personnel require the “four-set†principle to lubricate the parts of the lubrication diagram, and the amount of oil in the lubrication part must not be excessive.
3. The filter unit should be cleaned frequently to keep it clean.
4. The return oil temperature generally does not exceed 55 °C, and the temperature of each bearing does not exceed 60 °C.
5. Observe the operation of the equipment, whether there is vibration or not, and whether the sound is normal.
6. Always check the bolts of each part for looseness.
7. Observe the electrical instruments and technical conditions of all electrical appliances at any time.
8. Check for looseness between the moving cone liner and the fixed liner.
9. Maintain equipment hygiene and sanitation.
Third, maintenance procedures
1. Maintenance period: minor repair for 1 month, medium repair for 12 months, overhaul for 18 months.
2, maintenance content:
1) minor repair
I. Check the lubrication and wear of bearings, tapered sleeves, eccentric bushings, base bushings, break bearings, bevel gears, etc., and adjust the clearance.
II. Tightening screws
III. Clean the oil circuit and dust water system, remove the oil leakage, add or replace the oil, and repair the oil pump.
IV. Check the wear of the umbrella panel and each of the pull plates. [next]
V. Check the clearance and the amount of movement of the drive bearing and replace if necessary.
VI. Motor bearing cleaning and refueling.
2) Zhong Xiu
I. The round grinding is completely disassembled, the gear meshing clearance is adjusted, and the upper, middle and lower discs are inspected or replaced.
II. Replace the moving lining and fixing the lining.
III. Replace the tapered sleeve, the machine 2 bushing, the size of the bevel gear, the drive shaft, and so on.
IV. Scrape spherical bearings or replace, weld spherical bearings, etc.
V. Welding repair feed funnel, protective cover, body plate, etc.
VI. Replace the drive shaft assembly or the crush cone assembly.
VII. Replace the oil pump.
3) Overhaul
I. Replace or repair the machine base, handle the spring bolt hole of the machine base, the machine seat ladder, the crack of the machine seat rib, re-cast the foundation, etc.
II. Replace the support ring, adjust the ring part, replace the cone, the main shaft, the eccentric shaft, the bowl-shaped bearing seat, and the size of the bevel gear.
3, maintenance quality standards
I. The horizontal deviation of the base should be less than 0.1mm per person.
II. The displacement error of the center line of the new and old stands is not more than 2mm.
III. The shaft of the drive shaft should be no more than 0.25-0.3mm.
IV. The matching top clearance of the bearing and shaft of the sliding bearing should be 0.24-0.4mm, the side clearance should be 0.1-0.2mm, and the contact point should be 1-2 points to open the oil groove.
V. The side of the transmission gear gap is 2.5-3mm, and the radial clearance is 3.5-4.3mm.
VI. Gear meshing is normal.
VII. The support ring part is firm and reliable, and the oil hole is unblocked.
VIII. The gap between the eccentric bearing and the bushing is 1.5-2mm, the gap between the vertical shaft and the taper sleeve is 2.5-3mm, and the lower part is 8-10mm. .
IX. The spherical contact width of the spherical bearing and the crushing cone shall be 1/3 - 1/2 of the radius of the spherical bearing, the contact point shall not be less than 1 point per square centimeter, and the wedge gap of 0.5-1 mm shall be maintained along the inner circumference.
X. inlet holes, water holes, an annular sealing groove, the water spray orifices point ore, iron rust, raw sewage and the like must be cleaned, a blowhole may not be arbitrarily expanded or reduced, and the dust seal preventing crushing cone The dust ring gap should be 1.5-3mm.
XI. When installing the moving cone liner, the deflection should not exceed 3mm.
XII. Carry out trial operation, empty running for 15-30 minutes, all parts should have no abnormal vibration and noise, and the support ring should be free from sloshing and jumping. The vibration of the machine base is not more than 0.5mm. .
After the large and medium repair of the cone crusher, the acceptance must be fulfilled.